Showhome about to open

Stagers arrived today to set up the house and I’ve been working through some details as well. Current inventory in the market appears to be very low, so we are listing in advance of the classic ‘spring rush’. The project was efficiently run, and is now approaching the end of month 7. What I find fascinating is we are basically 200 days into construction from a hole in the ground to an operating show suite. Backing out holidays and Sundays, we need to finish more than 0.5% of the build per working day (for each house), through all weather conditions. It is a tribute to my professional and skilled trades that this is even possible to conceive of being achievable to finish that much work. Looking back there were days where I had 5-6 crews on site and significant orchestration to referee this chaos was needed. Plenty of construction lessons learned as we navigate these tricky schedules.