Thoughts on the epermit system

The city has made some real gains on modernizing the application and inspection procedures for new low density homes such as my new semi detached project.  It has moved in a big way to electronic submission of plans and documents plus online booking and review of inspection outcomes.    

I’m a fan of this process.  It contributes to the productivity of the business operator when files can be moved around and approved paperlessly and appointments booked without even a phone call.  

There must be productivity improvement at city hall as well.  This is good because this summer getting staff to process permits was at times really difficult.  The staff appears to have massive holiday periods where little to no work is done. That really conflicts with how urgent it is to get work started during the warm season (warm season appears to be about 4 months long).  Any tactics to improve processing speed are welcome. The last dp took 5 painful months to get released and we were in jeopardy of losing a precious month of the best time to build.   We are pushing now big time to catch up.  Stucco season countdown clock is definitely ticking louder each day.     

 

 

IMG_2493.PNG

As work progresses the city system allows the builder to access more inspection functions.  This should free up the 311 operators to deal with more pressing concerns.  I’m definitely over the hump of the learning curve with this stuff.  Now to synchronize it with my construction management system... possibly too much to ask.  

What political party is worse for the building industry?

Isn’t it easy to fall into the trap of resenting the insufferable fools in command of the political parties?  I’m not sure who is worse, Trudeau or Scheer, but they could be equally horrid. Trump is a real trouble maker as well, and he is from a parallel universe. How this relates to the ‘little guy’ has recently become  even more clear.  The metal tarrifs are now causing some havoc with pricing of basic goods such as tin ducts.  This is passed onto the builder through rising prices.  It seems that every policy change has the same outcome, rising cost and margin compression and it hits the business owner earliest.  Are we going to enter into an unhealthy stagflationary cycle?  Appears so.  

 

FullSizeRender.jpg

After they screw up the supply management system further maybe they can cause some more harm to the building industry.   

The rising price of everything

Lumber continues to be a building material cost wildcard.  There is always a reason for this too, either government manipulation and tariffs, a recent favourite, or fires in B.C. 

Regardless of the reason, cost escalates randomly and often a lot   You do see occasional drops in prices for OSB, right now the sheet is down $2 from last year.  Structural components are up though, and by more than 30%.  This is really driving up the cost of my project so I’m frustrated.  We found a few savings in an earlier phase of work but it is all offset by the framing package.  

Here is a shot of some pricing last year and this year for the same product.  

 

 

 

 

FullSizeRender.jpg
FullSizeRender.jpg

Foundation pour, Richmond semi

The cribbing is almost complete now at the Richmond semi.  With the form strip booked to start tomorrow our new basement will be unveiled.  Always a positive start to the job when you have the walls poured in favourable weather. 

 

IMAGE.JPG

Braced and poured.  Stripped tomorrow and backfill next week.  

 

IMAGE.JPG

Update - and now we have it stripped and can begin the prebackfill process.  

Footing details

My usual footing/cribbing crew arrived at the new job site along with the structural engineer.  The homogenous sandy condition of the excavation has been very interesting.  This part of Richmond must have been an area of heavy deposition during the ice age melt down to have left behind this much sediment. Soil bearing of course is more of a concern on these sandy soils.  End result is just add some width and rebar to the footing and carry on.  

 

IMAGE.JPG

This footing would be a nice beach.  the soft conditions make for a much easier place to work in. 

Goodbye 2111, we won't miss you

The 2111 house found itself in the back of the dump truck early this morning.  With the house removed we can start the real work. 

Thanks ‘troublemaker Neighbour’ who already accused us of operating without a permit and without removal of the asbestos.  He called the city after raising a large ruckus and eventually the city told him to go away.  Its nice when the city staff get involved and take my side in a dispute before it can escalate.  These projects cost a lot of money to run by the day and we don’t need work stoppages, particularly when we’ve done the right thing and fulfilled all our commitments.

 

IMAGE.JPG

A few dump runs and the house is completely gone. 

The City loves money

City hall has been ramping up its fee structure on everything lately, with the offsite levy really kicking in, the unfair way it calculates the asphalt degradation charges, and the surface improvement estimate.  With the surface improvement estimate, the work is done at City rates, so there is no way to get the cost down. I find the surface improvements can be quite costly, especially when they try and get you for the streetlights as well.  I never understood how a builder should pay for new streetlights that are on City property, and are used by the entire City.  It isn't like a homeowner has a switch to shut off a streetlight near their bedroom window.  Fortunately at the recent project there were no streetlights, so that could not be used as a way to increase the fee.  The concrete cost is the largest I've seen to date on any of my projects.  This is a byproduct of the lack of lane access so we need front driveways and new curbs.  I guess we need to hope that the attached garage built form is attractive to the future owners so we can recoup the cost of the work. 

It always hurts when these fees kick in before construction begins.  These fees take a lot out of the budget that is needed to build the house, and the surface improvement wont be done until 2019.  It would be far better if the surface imp…

It always hurts when these fees kick in before construction begins.  These fees take a lot out of the budget that is needed to build the house, and the surface improvement wont be done until 2019.  It would be far better if the surface improvement was paid for when it was built, not in advance. That is like financing City Hall operations for free for a year, and builder financing cost is far higher than City financing.

Rowhouse move in day

A few finishing touches and appliance adjustments and the first rowhouse residents are moving in.  One townhouse unit remains available, will start to market it next week.  

 

IMAGE.JPG

Rowhouse occupancy permit granted!

We started the rowhouse project in mid November and did some seriously difficult work in adverse conditions all winter. Occupancy was granted today, July 27th.  That timeline suggests construction was around eight months.  Occupancy is a huge relief.  Once again finishing a project has proven to be really difficult with many hours invested.  

 

IMG_2312.PNG

Starting house #6&7 for 2018

The fences are up so that is a definite sign, I am ready to demolish a house and we can get building soon.  This will be the sixth and seventh houses I will be constructing in 2018.  That is a lot of construction and I’ve been super busy this year.  The schedule has worked out fairly well as we are wrapping up the Threeplex and once that is done I will have time to focus on the new semi.  

 

IMAGE.JPG

this house has only a few days left and it will be crumpled up in a dumpster.  

Making sense of roof layouts

At the building permit stage the lumber yard supplying the structural components creates the truss and floor layouts.  They do this on a proprietary software that produces considerable detail.  I attempt to review each page in order to get a greater understanding of what I am commiting to buying and building.  The renderings sure help a lot! 

 

IMG_2267.PNG

These are the roof layout rendering of my upcoming project.  This is very appealing to me because I like simple roof lines that drain well and are predicable and easy to shingle. Most of all I want the roof cavity to have clear and obvious ventilate pathways that won't collect frost in the winter during a heavy snow year.  This roof passes all of my criteria.  What we have seen, especially last winter, is many roof failures from ice jammed valleys and snow blocked vents.  Those are a nightmare to deal with.  

Exterior completion and Deck building continued

More aluminum deck framing at the rowhouse project.  At this stage this is really the last thing to do outside, with the exception of the garage door fiasco. 

I will be calling what is known as the development completion inspection shortly. It is necessary to get this in order to receive an occupancy permit. I'm hopeful the city will overlook the lack of garage doors when this is done.  I ordered custom garage doors that were going to be perfect for my project however the supplier sold them to another installer for an unknown reason.  So my custom garage doors that I waited a month for were never even going to be arriving.  Apparently the wait is four more weeks for new doors to be made. 

 

IMAGE.JPG

This is a properly built deck frame.  We've learned a lot about this product since the first deck started.  

Custom metal signage detail

The live33st.com rowhouse is a large enough project that it seems able to absorb any amount of custom detailing. Instead of the usual tacked on house numbers I've elected to go with a custom fabrication and tested out a new supplier. Win win so far.   

 

IMAGE.JPG

Nice font.  Seems to really work with the background.  I'd like to accept partial credit for the concept.   

Rowhouse deck building - all allumimum and composite material

We are continuing the theme of material and technique experimentation at the rowhouse by incorporating a new deck system for the townhouse units.  This is interesting because it likely will either be a total disaster, such as the material does not withstand the temperature fluctuations, or a huge success, and the material will prove to be durable and moisture free for many years.  At this point I am still debating what is the more likely outcome.  

 

after much screwing around and redoing screwed up work, the structure begins to come together.  actually this is a photo of the  original screwed up version of the frame.

after much screwing around and redoing screwed up work, the structure begins to come together.  actually this is a photo of the  original screwed up version of the frame.

And the newly fixed frame is almost 'decked out' in the new composite boards.  looks good so far, but will it survive the harsh Calgary climate?  We will find out soon...

And the newly fixed frame is almost 'decked out' in the new composite boards.  looks good so far, but will it survive the harsh Calgary climate?  We will find out soon...

Demolition permit - how to apply just became a whole lot easier

UPDATE 2022 - the process is much improved thanks to the CICBA and the city improved its internal procedures, as has Atco gas. Goodbye and good riddance to the $4250 deposit fee!!!

UPDATE 2018 In an earlier post I described how awful it was to get a simple demolition permit from the City of Calgary.  It required multiple trips to City Hall to essentially apply, pay a security deposit, re-apply, and finally get issued the permit.  All of this took a lot of time, parking, driving, waiting in line, etc.  

Much of this wasted time is now improved upon as the applicant can apply online, from anywhere, at any time.  No more crowded waiting room lineups at the permit desk.  All documents are uploaded through the vista/e-permit system, which is quite easy to navigate.  The process still requires a trip downtown to pay the $4250 deposit, something that also should be changed as it needs a bank draft and a trip to the bank to get it, but the remainder of the process works well.

The key change they made other than online application, is the availability of the disconnect sheet.  The disconnect sheet is the document that allows the collection of atco, enmax, and water department signatures. That remains a perilous and difficult process to get the signatures in a timely manner, but at least it can be done more easily.  So the City initiative to remove red tape has finally brought me some efficiency benefits, what a relief!

And here it is, my first online demo permit app.  What a tremendous improvement over the formerly archaic system.  It is a real time and cost saving improvement at City Hall!

And here it is, my first online demo permit app.  What a tremendous improvement over the formerly archaic system.  It is a real time and cost saving improvement at City Hall!

 

 

Inner city lane paving

You'd think that inner city neighborhoods, some built around 75 years ago would be largely complete.  In the case of Calgary youd be mistaken.  Calgary loves to tear out the old stuff and replace it.  Most of the lanes in these older areas were never even paved.  Decades later this lack of asphalt has become a real pain.  Now we have multiple trash bins and more density every year. Along with the new houses comes higher expectations.  Those individuals paying an average of $6k per year in property tax tend to want the city to provide services.  

Paved lanes isn't a service the city offers unless the residents offer to pay for it via a vote.  The lane between 34 and 33 st which happens to be my block is currently being paved. After the snow and hideous cold winter we suffered through where our lane became impassible for weeks at a time, paving will be a welcome relief.  

Unfortunately some of the newer houses (and older ones too) were poorly designed and the grades don't work with the new lane. This could be a major garage access problem. Grades are a tricky issue and often I struggle with blending in the old and new grades. I didn't dig my own garage as low as it optimally could be and this is truly aggravating.  But compared to my northern neighbour mine is at least serviceable. 

 

 

IMAGE.JPG

This is what happens when the grades aren't considered at the time of construction.  

Greening up the rowhouse

After many hard months of building it is always a relief to see the landscaping work nearing completion.  Laying sod and planting some trees makes a big difference on a corner site in particular.  The rest of the month will be a push to get it all wrapped up in time for the clients to move in. So far we appear to be on schedule and possibly even a little ahead on the first townhouse.  

 

IMAGE.JPG

Sprinklers, loam, sod, mulch, trees.   

IMAGE.JPG

And water is hooked up so sprinkler system can function.  Much tuning still required but the sod will survive the July heat.  

Trim details

Rowhouse work continues this stampede weekend with more floor install and the finishers lockout in the first house. Baseboards, door hanging, door hardware and closet rods are some of the lockout tasks. Next up it is time to get the decks done and the garage doors hung, plus begin the final inspections.   

 

IMAGE.JPG

Not particularly photogenic work underway inside the rowhouse.  More to come next week.  

Landscaping progress - rowhouse

The landscapers are on day 2 of the rowhouse project.   Fill was added in some areas to reach closer to final grade and the fence posts drilled and grouted in place.  The irrigation contractor has also installed the network of pipe and nozzles for sprinklers.  Having a programmable sprinkler is a real time saving luxury item. Without sprinklers keeping the various patches of sod and trees watered is difficult.  Note we had to leave a lot of conduit under the sidewalks to allow passage of the water pipe. Without that install is a big problem.  

 

IMAGE.JPG
IMAGE.JPG

Ready for loam and sod