Once again, I seem to have got caught up in a slow approval process for my next project, a three unit rowhouse. We are into the sixth month of the DP process. We have made every effort to comply with the requirements of the multi family zone, however it seems from my perspective the City lacks a performance standard for turning around approvals.
The process of permitting a project starts with the DP. Without this no forward progress can result. In order to submit our DSSP for approval (this alone takes 5 weeks), we need the DP. Without the DP we can't submit the BP either. And without the BP we can't get the lumber yard to design the joists and truss package, the most essential part of the BP package that is out of my hands to create. I can have the design company prepare the BP files early (we are doing so), but the danger is we do a lot of design work only to have to change it later if for whatever reason the DP needs to be changed.
All of these delays can consume an entire building season. I knew this from the start so tried to get my DP in as early as possible (November), clearly, this was not early enough. What is further frightening is the City tends to work a lot slower over the City months because the staff enjoy a lot of paid vacation time.
It comes back to a lack of a clear service standard for the staff to issue permits in a reasonable time. The permits could be done a lot faster, but I have come to believe it is a conscious choice internally to continue to add procedural steps and reviews that slow the process. I think this comes from the lack of customer focus of the City related to planning. The staff don't see the builder as the customer to be served. Their motivation and reward system is directed elsewhere. If the staff salary depended on prompt issuance of permits, I would likely have all my permits in place and a construction start date. Instead I just have an ugly carrying cost for the property and a summer building season slipping away day by day.