The drywall crew was back for one more job, blowing the loose fill insulation into the attic cavity. We are putting at least r40 in there, the new code is requiring r50, so we will be very close to what that depth of fill is.
Tomorrow we are accepting delivery of the finishing package, and more exterior work is planned for the front of the building. The schedule is proceeding nicely almost with a momentum of its own creation. Sounds like time for me to update the schedule and predict more accurately when I will need the tile!
Jiggi is a multitalented guy. Here he is running the blow in machine.
The loose fill insulation is now installed into the attic cavity.